Exploration & Production·Friday, November 20, 2026

Ottawa and Newfoundland Approve Equinor's C$14 Billion Bay du Nord Plan, Setting Up a 2027 Decision

Shell will hold 30% and Equinor 70% of the field, which Equinor puts at more than 400 million barrels in its first phase, with first oil targeted for 2031.

Canada and Newfoundland and Labrador jointly approved Equinor's development plan for the Bay du Nord oil project on Nov. 20, clearing the plan before Equinor and Shell decide in early 2027 whether to sanction the C$14 billion development.

The approval covers a field about 500 kilometres east of St. John's in the Flemish Pass Basin. According to the Newfoundland and Labrador government, it is the first new standalone offshore development in the province since Hebron and its first in deepwater.

For the province, the project would add a new producing field in the early 2030s. Natural Resources Canada estimates it would generate about C$20 billion in government revenue over a 20-year operating life. That projection assumes a sanction decision that has not yet been taken.

Equinor and Shell carry Bay du Nord toward sanction

Ownership has changed twice this year. On July 6, Equinor agreed to buy bp's interest, which would have left it with 100% of the project. On Oct. 9 it agreed to sell 30% to Shell, keeping 70% and the operator role. The Canadian Press reported that bp's stake was 37.2% and that neither deal's price was disclosed.

Philippe Mathieu, Equinor's executive vice president for Exploration and Production International, said in the Oct. 9 Equinor release: "We are pleased to welcome Shell as a partner in Bay du Nord."

The first phase combines the Bay du Nord field, discovered in 2013, and the Cambriol field, found in 2020. Equinor puts recoverable resources in that phase at more than 400 million barrels, in water 600 to 1,170 metres deep. Oil would flow through subsea wells to a floating production, storage and offloading vessel, with front-end engineering and design still under way. Equinor says that work focuses on capital efficiency and execution planning. The concept also leaves room for later tiebacks, and Equinor lists Cappahayden, Harpoon and Baccalieu as potential additions.

Natural Resources Canada put the project's capacity at up to 160,000 to 175,000 barrels a day when the province and Equinor signed their benefits agreement in March. Dividing the C$14 billion investment estimate by that range gives roughly C$80,000 to C$87,500 for each daily barrel of capacity, by Oil Authority's calculation.

The regulator sets conditions before a final investment decision

The Canada-Newfoundland and Labrador Offshore Energy Regulator announced on Nov. 20 that it had approved the Development Plan together with an updated Benefits Plan. Equinor filed the revised benefits plan after the public review so that it matched the provincial benefits agreement. The approval carries conditions, which the regulator lists in its Decision Report.

Natural Resources Canada said the regulator approved the application on Nov. 4, after a 60-day engagement period with the public, industry and Indigenous groups that ran from June 22 to Aug. 20. The federal government gave the project a positive environmental assessment in April 2022. Drilling is expected to start in late 2029 or early 2030, with first oil targeted for 2031.

The province's terms are the other part of the deal. Its March agreement gives it an option on up to 10% equity and projects up to C$6.4 billion in direct revenue from the first phase. Equinor had paused the project in 2023 for up to three years before those terms were reached.

Premier Tony Wakeham said in the province's March 3 release: "Newfoundland and Labrador is officially back in the oil and gas business." Natural Resources Canada said at the time that Ottawa was committed to helping de-risk the project.

Capital is moving into the province's offshore from several directions. Oil Authority reported on Nov. 15 that Ithaca Energy agreed to buy Suncor Energy's Newfoundland offshore stakes for C$1.2 billion. Bay du Nord, by contrast, would be a new field rather than a change of ownership.

Equinor has not committed to build. It has said a decision depends on market conditions, regulatory approvals and each partner's internal processes. Equinor and Shell are due to take that decision in early 2027, and the province's choice on its 10% equity option follows from it.

Sources and methodology

Oil Authority calculations: C$14 billion investment estimate divided by 160,000 and 175,000 barrels a day of capacity.